Road Resurfacing 2022

PUBLIC NOTICE OF CONSTRUCTION WORK

Hot Mix Asphalt Resurfacing of Municipal Roadways 2022

September 6, 2022

The Town of Shelburne runs an annual resurfacing program in order to maintain our road infrastructure and address road conditions.

The resurfacing of municipal roadways within the Town of Shelburne will be underway starting September 11, 2022 by The Murray Group Ltd.

The resurfacing will include milling and removal of existing roadway material, and supply and placement of new asphalt.

Traffic impacts can be expected during the construction period.  There is also a potential for noise associated with construction to be heard during this time.

Project Schedule 

The project is scheduled to begin on Monday, September 11, 2022, at approximately 7:00 A.M. and completed tentatively on Friday, October 7, 2022. Work will be performed between the hours of 7:00 a.m. and 7:00 p.m., Monday through Friday.

Residents should be aware that this schedule is subject to change due to weather impacts and other unforeseen construction delays.

Project Location

The 2022 Resurfacing of Municipal Roads Project includes the following locations:

Site Number

Location

1)

 

Greenwood Street (Fiddle Park Lane to #413 Greenwood Street & #401 Greenwood Street to Robert Street)

2)

Birch Grove (Cedar Street to Maple Court & #129 Birch Grove to Maple Court)

3)

Greenwood Crescent (Intersection near Northwest Cul-de-Sac)

4)

Laneway (Main Street to First Avenue)

5)

Owen Sound Street (South Bound Lanes, Main Street East to First Avenue)

6)

Industrial Road (Bend near #715 Industrial Road)

7)

Royal Canadian Legion Boulevard (Northeast Corner of William Street & First Avenue)

Please be aware that temporary full road closures may occur during key components of the construction project, but care shall be taken by the contractor to allow full access to local traffic.

A map outlining the project locations has been attached for your reference.

Map of Work Areas

Greenwood Street (Fiddle Park Lane to #413 Greenwood Street & #401 Greenwood Street to Robert Street)
 Road Resurfacing - Area 1 - Greenwood Street
Birch Grove  (Cedar Street to Maple Court & #129 Birch Grove to Maple Court)
Road Resurfacing - Area 2 - Birch Grove  
Greenwood Crescent (Intersection near Northwest Cul-de-Sac)
Road Resurfacing - Area 3 - Greenwood Crescent  
Jelly Lane (Main Street to First Avenue)
Road Resurfacing - Area 4 - Jelly Lane  
Owen Sound Street (South Bound Lanes, Main Street East to First Avenue)
Road Resurfacing - Area 5 - Owen Sound Street  
Industrial Road (Bend near #715 Industrial Road)
Road Resurfacing - Area 6 - Industrial Road  
Royal Canadian Legion Boulevard (Northeast Corner of William Street & First Avenue)
Road Resurfacing - Area 7 - Royal Canadian Legion  

Scope of Work

The work to be completed under this project includes:

  • Milling of existing top course asphalt pavement
  • Adjustments to maintenance holes and catch basin structures
  • Hot mix asphalt resurfacing
  • Full depth resurfacing, ditching and driveway culvert replacements (Industrial Road only)

Traffic Impact

Residents can expect temporary road closures to through traffic at the project locations over the construction period.  This includes not having access to your driveways for short durations during critical components of the project (milling and paving). Flag persons will be on site at every location to ensure traffic safety is always maintained.

At the end of each working day, you will have full access to your homes or businesses. The Town of Shelburne advises residents to:

  • avoid parking overnight on the roadways under construction.
  • remove vehicles from the roadways prior to commencement of this proposed work.
  • drive with elevated caution at reduced speeds through all construction zones.   

Contact Information 

Please do not hesitate to contact us if you have any questions.

Primary Contact:

Blake Aram, Field Inspector, S. Burnett & Associates Limited
Phone: (519) 217-1091
Email: blake.aram@sbaengineering.com

Secondary Contact:

Jamie Kaske, Operations, Parks & Facility Clerk, Town of Shelburne
Phone: (519) 925-2600 ext. 261
Email: jkaske@shelburne.ca

Please see Hot Mix Asphalt Resurfacing of Municipal Roadways 2022 to view this notice as a PDF document. 

Contact Us

Administrative Office 
203 Main Street East
Shelburne, ON L9V 3K7 

Email: info@shelburne.ca
Phone: 519-925-2600
Fax: 519 -925-6134

Sign up to our Newsletter

Stay up to date on the town's activities, events, programs and operations by subscribing to our eNewsletters.

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.