Road Resurfacing 2023

Updated September 6, 2023


PUBLIC NOTICE OF CONSTRUCTION WORK

Hot Mix Asphalt Resurfacing of Municipal Roadways 2023

The Town of Shelburne runs an annual resurfacing program in order to maintain our road infrastructure and address road conditions.

The resurfacing of municipal roadways within the Town of Shelburne will be underway starting August 29, 2023 by Forest Contractors LTD.

The resurfacing will include milling and removal of existing roadway material, and supply and placement of new asphalt.

Traffic impacts can be expected during the construction period.  There is also a potential for noise associated with construction to be heard during this time.

Project Location, Map and Schedule

Construction works are set to begin for Site 2 on Tuesday August 29, 2023 at approximately 6:00am and completed tentatively on Thursday August 31, 2023.

The remainder of the project schedule is to be confirmed and the webpage will be updated accordingly.  

Residents should be aware that this schedule is subject to change due to weather impacts and other unforeseen construction delays.

The 2023 Resurfacing of Municipal Roads Project includes the following locations:

A map outlining the project locations has been attached for your reference.

Industrial Road from 720 Industrial Road – Centennial Road - Start Date September 14, 2023 

Construction works are set to begin on Thursday September 14 at approximately 6:00am and completed tentatively on Friday September 15, 2023. 

Road resurfacing Area 1 

Fourth Avenue from Owen Sound Street – Gordon Street and Gordon Street from Fourth Avenue to Third Avenue - Start Date Tuesday August 29, 2023 

Construction works are set to begin on Tuesday August 29, 2023 at approximately 6:00am and completed tentatively on Thursday August 31, 2023. 

Road resurfacing area 2

Fiddle Park Lane from Berry Street – Orvis Crescent - Start Date September 11

Construction works are set to begin on Monday September 11 at approximately 6:00am and completed tentatively on Friday September 15, 2023.

Road resurfacing Area 3

Greenwood Street from Main Street – Municipal Laneway (Berwick Lane) - Start Date September 12  

Construction works are set to begin on Tuesday September 12 at approximately 6:00am and completed tentatively on Friday September 15, 2023.

Road resurfacing Area 4
Municipal Laneway from Gordon Street – First Ave and Second Ave (Station Lane and Jelly Lane) - Start Date September 13
Construction works are set to begin on Wednesday September 13 at approximately 6:00am and completed tentatively on Monday September 18, 2023.Road resurfacing Area 5

Please be aware that temporary full road closures may occur during key components of the construction project, but care shall be taken by the contractor to allow full access to local traffic.

Scope of Work

The work to be completed under this project includes:

  • Milling of existing top course asphalt pavement
  • Adjustments to maintenance holes and catch basin structures
  • Hot mix asphalt resurfacing
  • Full depth resurfacing, ditching and driveway culvert replacements (Industrial Road only)

Traffic Impact

Residents can expect temporary road closures to through traffic at the project locations over the construction period.  This includes not having access to your driveways for short durations during critical components of the project (milling and paving). Flag persons will be on site at every location to ensure traffic safety is always maintained.

At the end of each working day, you will have full access to your homes or businesses. The Town of Shelburne advises residents to:

  • avoid parking overnight on the roadways under construction.
  • remove vehicles from the roadways prior to commencement of this proposed work.
  • drive with elevated caution at reduced speeds through all construction zones.   
Contact Information

Please do not hesitate to contact us if you have any questions.

Primary Contact:

Blake Aram, Field Inspector, S. Burnett & Associates Limited
Phone: (519) 217-1091
Email: blake.aram@sbaengineering.com

Secondary Contact:

Jamie Kaske, Operations, Parks & Facility Clerk, Town of Shelburne
Phone: (519) 925-2600 ext. 261
Email: jkaske@shelburne.ca




Contact Us

Administrative Office 
203 Main Street East
Shelburne, ON L9V 3K7 

Email: info@shelburne.ca
Phone: 519-925-2600
Fax: 519 -925-6134

Sign up to our Newsletter

Stay up to date on the town's activities, events, programs and operations by subscribing to our eNewsletters.

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.